Centennial Park power upgrade works (June-August 2018)

Published on 25 Jun 2018

Works will commence today in Centennial Park to install and supply 3 phase power to some areas of the Park including the Education Precinct, Discovery Centre and Brazilian Fields.

Due to the complexity of Centennial Park, the project has been split into two phases to safely deliver the electrical works as well as minimise any impacts on park users.

To safely facilitate the trenching works there will be some temporary closures on some internal roads, pathways and facilities including:

  • Road closure on Loch Avenue South: Monday 25 June (6.00 am to 6.00 pm)
  • Loch Avenue sports field closure: 25–29 June
  • Discovery Centre closure: 2-6 July
  • Partial Horse Track closure: 23-27 July

Works will be completed by end of August 2018.